February is a big month for Duke Energy to move coal ash out of its Dan River site.

With a new two-mile rail spur in place and machines moving material from large “ash stacks” – soil-covered mounds of coal ash - Duke Energy expects to double its current rate of progress.

CAMC
Dave DeWitt

The North Carolina Supreme Court has sided with Governor Pat McCrory in a case against leaders in the General Assembly.

Image of bottled water provided by Duke Energy to families affected by the coal ash spill.
Dave DeWitt / WUNC

Next month will mark two years since 40,000 tons of coal ash and 27 million gallons of contaminated water flowed into Dan River as a result of a Duke Energy spill. The electric utility giant is working to clean up the coal ash at multiple sites across the state.

But legal infighting and regulatory delays have stalled progress at 10 of the 14 sites. Meanwhile some residents are afraid to drink out of their tap.